How to read the demand plan#
For: Manager | Admin You’ll need: A driver, some recorded history, and a labor standard.
The demand plan is the page you actually work on: one week at a time, one row per day, showing what Shiftavo expects and what staffing that implies.
Open it#
Go to Planning → Demand → Demand plan.
Pick the ‘Location’ and the ‘Driver’ at the top of the page.
Move between weeks with the arrows, or jump back with ‘Today’.
What the columns mean#
Column |
What it shows |
|---|---|
‘Day’ |
The date. Click the row to expand its interval detail. |
‘Actual’ |
What was really recorded, for days that have passed. |
‘Forecast’ |
What Shiftavo expects, from your history — or your own number, marked ‘Yours’, if you set one. |
‘Your day forecast’ |
The field where you type your own number for the day. |
‘Required hours’ |
The labor hours the day implies, across all resolving standards. |
‘Peak heads’ |
The largest headcount any one position needs in a single interval of that day. |
‘Required hours’ and ‘Peak heads’ are derived: change the forecast or a labor standard and they follow.
When the page is empty#
If you see ‘Nothing to plan against yet.’, there is no active driver — an Admin sees a ‘Create your first driver’ button there. If the rows exist but required hours stay at 0, no labor standard resolves for that position and time; see How to create a labor standard.
What you can do from here#
Disagree with a day? Type your own number — How to set your own day forecast.
Want to know why? Click the row — How to read the day detail.
Ready to build shifts? Click ‘Create shift skeletons’ — Shift generation.
How current the numbers are#
The forecast is rebuilt every night for the whole horizon — a little over a year ahead — and the required hours are recomputed in the same pass, so the two can never disagree. Recording a value today shows up in tomorrow’s forecast.
Verify it worked#
Pick a past week: the ‘Actual’ column is filled in, and ‘Forecast’ sits close to it. A large, consistent gap is a signal — check Forecast vs actual.